Alert Management
DEPT 2 — 2026 Turnaround — Day 14 of 45
LIVE
Total Alerts
9
Critical
2
Warnings
4
Acknowledged
0
Active Alerts (9)
CRITICAL
Reactor R-301 SPI dropped to 0.78 — trending 22% behind schedule. WYATT refractory structure crew at 79% CPI.
MSCC / RX
WYATT - REFRACTORY STRUCTURE — 07:12
SPI: 0.78
CRITICAL
Regen section SPI at 0.85, CPI at 0.80. Cost variance trending -$42K over 3-day window.
MSCC / REGEN
WYATT - BM STRUCTURE — 07:15
CPI: 0.80
WARNING
Slide valve activities SPI 0.87 — 4 activities behind schedule. Duration overrun averaging 18%.
MSCC / SLIDE VLV
REPCON - BM — 06:48
SPI: 0.87
WARNING
ALKY exchanger bundle pulls running 12% over budgeted hours. REPCON-EXCH CPI at 0.88.
ALKY / EXCH
REPCON - EXCH — 06:30
CPI: 0.88
WARNING
Relief valve activities SPI dropped to 0.89. 4 of 64 activities behind schedule.
ALKY / RV
REPCON - BM — 06:15
SPI: 0.89
WARNING
WYATT-PF crew SPI at 0.88 on MSCC piping. 10 activities behind across unit.
MSCC / PIPE
WYATT - PF — 05:58
SPI: 0.88
INFO
All battery limit blind activities completed on schedule. 452 hours at 100% CPI.
ALKY / BLB
APACHE - SCAFFOLD — 05:45
SPI: 1.00
INFO
Shutdown phase complete for GASCON. All 120 activities finished on schedule.
GASCON / SD/SU
BWO - OPERATIONS — 05:30
Complete
INFO
ALKY shutdown phase complete. 185 activities, 2,664 hours at plan.
ALKY / SD/SU
BWO - OPERATIONS — 05:15
Complete